| Contract Title |
Proposed Widening of the Existing Penang Bridge From East Abutment (km0.4) to Pier 24E (km4.3) and From Pier 24W (km6.5) to Pier 69W
(km8.3) |
| Contract No. |
PBR/BW/UUD/BRIDGE/N3/05-004 |
| Employer |
Penang Bridge Sdn Bhd |
| Employer’s Representative |
Opus International (M) Berhad |
| Engineer |
HSS Integrated Sdn Bhd |
Main Contractor
|
UEM Construction Sdn Bhd |
| Contract Sum |
RM 409,000,000 |
| Contract Period |
143 weeks |
| Commencement Date |
27th December 2005 |
| Contract Completion Date |
22nd September 2009 |
| Bridge Structure Widening |
Low level viaducts from dual-2 lane to dual- 3 lane.
The structural widening of 4.80 m both side of the bridge
inclusive of 2.0 m paved shoulder |
| Length of Bridge to Be Widened |
5.76 km |
| Total Bored Piles |
588 nos. |
| Total Pilecaps |
292 nos. |
| Total Column |
292 nos. |
| Total Crosshead |
292 nos. |
| Total Precast Post-Tensioned Beams |
585 nos. |